Voltage ride through capability of the plant must be approved by
Ans✓✓✓ ERCOT
Any resource or customer owned switching device that can interrupt
flow 60kV/Greater must have an agreement with _____ to schedule
outages on Ans✓✓✓ TO
The resource entity representing a Non-Coordinated test must inform
ERCOT and the TO ___ hours prior to the proposed start of the test
Ans✓✓✓ 2
Lagging reactive tests should be performed during __ load periods
Ans✓✓✓ High
Leading reactive tests should be performed during __ load periods
Ans✓✓✓ Low
The ___ representing a generation resource shall be responsible for
scheduling reactive verification tests when requested by the resource
entity Ans✓✓✓ QSE
Resource entity owners of transmission facilities shall provide to ___ all
nominal transmission facility ratings Ans✓✓✓ ERCOT
, ___ must notify ERCOT of any changes in its transmission facility status
within ten seconds Ans✓✓✓ TO
Each ___ shall have a vegetation management program outlining
procedures to prevent transmission line contact with vegetation
Ans✓✓✓ Transmission Owner
The ERCOT LFC system shall deploy regulation service and __ __
energy service to provide satisfactory frequency control Ans✓✓✓
Responsive Reserve
A __ __ shall immediately notify its QSE and its interconnecting TO of
any change in AVR Ans✓✓✓ Resource Entity
Combustion Turbine Max governor droop setting Ans✓✓✓ 4%
Response to a TO voltage set point instruction shall be completed in no
more than ___ minutes from receipt of the instruction Ans✓✓✓ 5
If the ERCOT transmission grid condition requires breaker or switch
operation to disconnect a NON MW producing generator, it shall be
completed in no longer than ___ minutes Ans✓✓✓ 15
The RRS obligation is a minimum of Ans✓✓✓ 2300 MW