Twentieth Century Public contracting laws in North America have historically mandated
professional design services be purchased separated from the selection of contractors solely on
the basis of lowest responsible bid. T or F? - CORRECT ANSWER-True
Most Public Procurement statutes require the selection of design services be purchased on the
basis of lowest responsible bid? T/F? - CORRECT ANSWER-False
There are always at least three parties involved in every project delivery process; the Owner,
Architect and Contractor. T/F? - CORRECT ANSWER-True
It is recommended to get a contractor on board early during the business and planning stage of
a DB project to have the best opportunity to achieve all objectives. T/F - CORRECT ANSWER-
True
The primary goal in choosing a delivery method is to ensure that it will meet the Owner's
project objectives while at the same time allowing the project to be completed on time and
within budget? T/F - CORRECT ANSWER-True
CM @ Risk project delivery is faster than Design-Bid-Build, but can be slower than Design-Build.
T/F - CORRECT ANSWER-True
,Fast tracking a project and phased construction is possible using the CM @ Risk project delivery
method. t/f? - CORRECT ANSWER-true
The owner can pre-determine how a project's construction team will interact with him or her
and with each other through the selection of the delivery system. T/F? - CORRECT ANSWER-
True
Under DB contracting, the owner still takes the cost risk associated with unusual schedule
delays and extreme weather. T/F? - CORRECT ANSWER-True
Bridging is the passing off or assigning of an architect's partially designed drawings to another
architect or DB Firm. T/F? - CORRECT ANSWER-True
Project delivery selection influences when contractor gets on board. T/F - CORRECT ANSWER-
True
CM-as-Advisor may be added to any project delivery method. T/F? - CORRECT ANSWER-True
Under the CM @ Risk delivery system, any sub-contractors hired to work on the project will
enter into contract directly with the owner. T/F? - CORRECT ANSWER-False
Design - Build delivers equal or higher quality than DBB projects according to a comparative
study by CII and Penn State. T/F? - CORRECT ANSWER-True
In a GMP contract approach/payment the Owner and DB entity share the costs in excess of the
GMP established by the DB entity. T/F? - CORRECT ANSWER-False
The DB delivery method may include additional services such as site acquisition and financing.
T/F? - CORRECT ANSWER-True
, Idwp - CORRECT ANSWER-Integrated design work plan
PDRI - CORRECT ANSWER-Project definition rating index
BIM - CORRECT ANSWER-Building Information Modeling
What is the biggest item contributing to team failure? - CORRECT ANSWER-Absence of trust
Design manager - CORRECT ANSWER-Manages design information flow and deliverables.
Unique role that didn't exist before
Designer of record - CORRECT ANSWER-Manages design performance interface
Four primary phases of oversight - CORRECT ANSWER-Preconstruction, contract oversight,
close-out, and performance evaluation
Formal partnering typically results in mutually developing which items? - CORRECT ANSWER-A
charter, communication matrix, and an issue resolution ladder
What are the critical interfaces between designer of record and contractor? - CORRECT
ANSWER-Design&construct for value, design & construct to budget, design for constructibility,
and design& construct for quality performance
Three requirements of estimating - CORRECT ANSWER-Functional, performance, and
prescriptive