WITH 100% VERIFIED ANSWERS
\.The law that set into place stormwater regulations in the 1970s is -
ANSWERS-The Clean Water Act
\.Regulations for managing stormwater activity on a construction site
are outlined in the - ANSWERS-NPDES
\.When should you read and understand your project stormwater
pollution prevention plan - ANSWERS-Immediately after the project
awarded and before you begin any site work is
\.Which of the following is not an allowable stormwater discharge or
non-stormwater discharge - ANSWERS-Discharges are contaminated
groundwater
\.Construction activity may begin - ANSWERS-When the jurisdiction of
operation specifies you can start
\.Waters that sell anti-degration standards are placed on the _______
list - ANSWERS-303D
, \.SWPP certifications are signed by - ANSWERS-An officer of the project
owner or an officer of the general contractor.
\.TRUE OR FALSE: The document that must be completed signed and
submitted to the state to obtain authorization to discharge is the NOT -
ANSWERS-False
\.The notice of termination can be filed when - ANSWERS-All
construction inside and outside of the building is completed and the
final stabilization has been verified as complete
\.Operators on a construction site are the entity in charge of plans and
specifications and the entity who is - ANSWERS-Is in charge of daily
activities
\.You should have a SWPPP for your construction site because (3
reasons) - ANSWERS-1. Its documents stormwater management
2. Demonstrates your intent to manage stormwater on your site
3. It is required by law
\.A well constructed SWPPP for your site should be - ANSWERS-Site
specific