Test - CON 216 Modules 8-10 Exam
Identify the process for investigating suspected fraud
Question 1 of 13.
The Army has a contract with the Right-Way Company. A Right-Way employee tells the Army Contracting Officer that the company has been charging the contract with work that it performed for
(_) The Federal Bureau of Investigation
& The Department of Justice (DOJ)
() The Army Procurement Fraud Attorney
(U The Army Criminal Investigation Command (CID)
(| Mark for follow up
[ Save /| Retum Later] [ Summary] [ Next»]
, Test - CON 216 Modules 8-10 Exam
(DUPLICATE) Identify the need for a contract termination
Question 2 of 13.
Which of the followiWe a supply contract for default?
@i The contractor has delivered goods with minor, easily correctible defects which resulted from an error in the government design specification.
(_ The contractor submits a fraudulent claim for equitable adjustment.
() The contractor fails to make progress and timely completion is now unlikely.
(_ The contractor has failed to deliver any goods in a timely manner.
(I Mark for follow up
[ « Back ] [ Save / Return Later ] [ Summary ] [ Next » ]
Identify the process for investigating suspected fraud
Question 1 of 13.
The Army has a contract with the Right-Way Company. A Right-Way employee tells the Army Contracting Officer that the company has been charging the contract with work that it performed for
(_) The Federal Bureau of Investigation
& The Department of Justice (DOJ)
() The Army Procurement Fraud Attorney
(U The Army Criminal Investigation Command (CID)
(| Mark for follow up
[ Save /| Retum Later] [ Summary] [ Next»]
, Test - CON 216 Modules 8-10 Exam
(DUPLICATE) Identify the need for a contract termination
Question 2 of 13.
Which of the followiWe a supply contract for default?
@i The contractor has delivered goods with minor, easily correctible defects which resulted from an error in the government design specification.
(_ The contractor submits a fraudulent claim for equitable adjustment.
() The contractor fails to make progress and timely completion is now unlikely.
(_ The contractor has failed to deliver any goods in a timely manner.
(I Mark for follow up
[ « Back ] [ Save / Return Later ] [ Summary ] [ Next » ]