Which type of improvement (aggregated improvement) accounts for the largest cost in Amanzi?
Drill well
Installing UV and RO filters
Install public tap(s)
Installing RO filters
Explanation:
Drill well – 19% of the budget; Installing public taps
accounts for 43% of the budget.
Installing RO filters – 23% of the budget; Installing
public taps accounts for 43% of the budget.
Installing UV and RO filters – 8% of the budget;
Installing public taps accounts for 43% of the
budget.
Question 2/10
This given plot represents the net balance which is [cumulative_budget] - [cumulative_cost] plotted over time
(continuous):
, What is the significance of the change in the slope in January 2024?
The number of teams was reduced
significantly, so fewer jobs were
completed.
Improvements in Sokoto stopped,
reducing costs.
All well drilling was completed, meaning
less spending per source on average.
Teams started travelling less, reducing
their cost, and keeping teams on budget.
Explanation:
All well drilling completed… is incorrect because
wells were continually drilled until 2027.
Improvements in Sokoto stopped… is incorrect
because 4,000 jobs still had to be completed.
The number of teams was reduced… is incorrect
because no teams were fired.
Question 3/10
In the context of the Maji Ndogo water source improvement project, what would
COUNTROWS('project_progress') in a DAX formula represent in the real world?
The number of projects with a status of
TEST
Correct Answer
Answered in 1012.2333333333 Minutes
Question 1/10
Which type of improvement (aggregated improvement) accounts for the largest cost in Amanzi?
Drill well
Installing UV and RO filters
Install public tap(s)
Installing RO filters
Explanation:
Drill well – 19% of the budget; Installing public taps
accounts for 43% of the budget.
Installing RO filters – 23% of the budget; Installing
public taps accounts for 43% of the budget.
Installing UV and RO filters – 8% of the budget;
Installing public taps accounts for 43% of the
budget.
Question 2/10
This given plot represents the net balance which is [cumulative_budget] - [cumulative_cost] plotted over time
(continuous):
, What is the significance of the change in the slope in January 2024?
The number of teams was reduced
significantly, so fewer jobs were
completed.
Improvements in Sokoto stopped,
reducing costs.
All well drilling was completed, meaning
less spending per source on average.
Teams started travelling less, reducing
their cost, and keeping teams on budget.
Explanation:
All well drilling completed… is incorrect because
wells were continually drilled until 2027.
Improvements in Sokoto stopped… is incorrect
because 4,000 jobs still had to be completed.
The number of teams was reduced… is incorrect
because no teams were fired.
Question 3/10
In the context of the Maji Ndogo water source improvement project, what would
COUNTROWS('project_progress') in a DAX formula represent in the real world?
The number of projects with a status of