You notice that a project using the predictive
approach is behind schedule for four out of the
five weeks. You perform a trend analysis and
predict that the project will also be behind this
© 2025 Assignment
week. You are in the process of submitting a
Guru01 - Stuvia
change request to get the schedule back on
track. What process group are you in?
Expert
a. Initiating
b. Planning
c. Monitoring and Controlling
d. Closing Ans: c. Monitoring and Controlling
Explanation:
Domain:
I. Project Management Fundamentals and Core
Concepts
Objective:
, 2
01 - Becoming a Certified Associate in Project
Management (CAPM)
Jason was recently hired to create a new
product. The product will be complex and will
require many years to complete and involve
many stakeholders from various groups. Jason
has decided it will be best to break up the
product into smaller subprojects that are
© 2025 Assignment
managed separately. What is Jason managing?
Guru01 - Stuvia
a. Program
Expert
b. Portfolio
c. Project
d. Operations Ans: a. Program
Explanation:
A program consists of similarly grouped
projects.
Domain:
I. Project Management Fundamentals and Core
Concepts
, 3
Objective:
02 - Projects and Project Management
Which of the following are not project
constraints?
a. Scope, quality, and schedule
© 2025 Assignment
b. Scope, cost, and schedule
Guru01 - Stuvia
c. Resource, risk, and cost
Expert
d. Procurement, issues, and opportunities Ans:
d. Procurement, issues, and opportunities
Explanation:
Scope, quality, schedule, budget/cost, resources,
and risks are some of the most important project
constraints.
Domain:
I. Project Management Fundamentals and Core
Concepts
Objective:
, 4
02 - Projects and Project Management
In a project, laws, compliance, and regulatory
requirements are considered:
a. assumptions
b. constraints
© 2025 Assignment
c. negotiable
Guru01 - Stuvia
d. irrelevant Ans: b. constraints
Expert
Explanation:
Failing to comply with government agencies and
regulations can have an impact on a project, and
the government should therefore be considered
stakeholders. Any specifications and
requirements by the government would
therefore be considered constraints.
Domain:
I. Project Management Fundamentals and Core
Concepts
Objective: