Once we reach a WIP limit for a given state, this means that ______ . - Answers This identifies a
potential bottleneck to the flow and the team should focus on completing the tasks
When managing the Inflows of the Portfolio backlog, which of the following is true? - Answers
We should focus on the opportunities which show overwhelming value relative to its cost.
When managing outflows in portfolio planning, which is NOT considered a good strategy? -
Answers Focus on idle workers, not idle work.
Which one is NOT a principle of Kanban? - Answers Do all the work in a pre-defined timebox.
To calculate the Weighted Shortest Job First (WSJF) we need to know the duration and the
________ - Answers Cost of Delay
The measure from when work was requested to when work was delivered is known as the ____.
- Answers Lead time
What can we do if we have members in a team who work on items that represent different type
of work with different statuses? - Answers Use multiple swim lanes on the board for the
different types of work.
Kanban as a practice focuses on measuring flow, which means ______ . - Answers We want to
focus on how well the work is started and finished in our system.
Which of these items will NOT be found in the Portfolio Backlog? - Answers Feature
The measure of how many items flow through the board and are completed is known as the
____. - Answers Throughput
Which one is NOT a purpose of System Design? - Answers Provide a detailed and coded
prototype
The Open Systems Interconnection model (OSI) for networking which contains multiple
subsystems that communicate with the subsystem below it, is an example of a ______ -
Answers Closed layered design
Which design goal of client/server architecture means that architecture can work with an
increasing number of clients? - Answers Scalability
To create a desirable system design, we want the system to exhibit ______ cohesion and
_______ coupling. - Answers high, low