CMGT 2400 Final Exam Study Guide Questions and
Correct Answers | Latest Update
A group of Nurse practitioners is planning to purchase a 3-acre parcel of
property located inside the city limits. They hope to develop a small
office building that includes a clinic and other leasable space. They are
currently working with an architect
In which of the project delivery phases is the team currently engaged
Ans: Predesign
Assignment Expert
Identify the tasks the nurse practitioners must accomplish during the
predesign phase Ans: - assess the appropriateness of the site
Guru01 - Stuvia
- select a design team
- define building program
- identify governmental constraints
2026
One of the most critical features of the design development phase of the
©
building delivery process is Ans: making decisions about pragmatic
solutions for various building systems
Which of the following is not one of the required items of a set of
construction drawings Ans: Digital "walk-throughs"
A specification is a written document that provides information about
_________ of a given material Ans: quality
The CSI MasterFormat is a standardized organizational system for
specifications based on a numbering system. An example of a
specification number is 06 10 00. The number 06 in the example
provided above refers to a specifications group called Ans: a Division
The divisions in the CSI MasterFormat that architects are most concerned
with Ans: 2-14
, 2 for specific request mail
the city of Metropolis is seeking bids for fast-track construction of a new
City Hall Building and parking garage. The most likely way a contractor
will be selected is through Ans: Multiple price contracts
During the construction phase, the architect Ans: observes construction
on a regular basis
The project manual is composed entirely of specifications Ans: False
Which of the following aspects of design and construction is not
regulated by the building code Ans: Aesthetic qualities
Assignment Expert
The primary objective of a building code is to ensure that all new
construction and renovations provide a ____________ level of safety Ans:
minimum
Guru01 - Stuvia
Construction of a new building can only begin after Ans: An application
for a building permit has been approved and received by the owner
2026
The height of a guard rail and the clear space between members are
a_____________________regulation Ans: fire safety
©
Dimension of the stair treads and risers Ans: Life safety
Location of an exit access Ans: fire safety
The size and properties of a steel column Ans: structural safety
A prescriptive building code Ans: provides a clear description of what is
required to satisfy code requirements
The IBC has been adopted for use Ans: by many states in the US
Which of the following factors are not used in the building code to
determine the allowable height and area of a building Ans: land use
the occupancy i one of the most important considerations when
determining the level of hazard present in a building. Which of the