A SWPPP site map will show all of the following except
-locations of BMPs
-Notices of Violation
-phasing and sequences
-limits of disturbance - correct answer- Notices of Violation
Common types of erosion include all the following except
-gully
-sheet
-rill
-sedimentation - correct answer- sedimentation
Hiring workers who are not authorized or not executing the WV program
can result in what
-construction sitre closure
-situational audit
-additional training
-all of the above - correct answer- all of the above
, If a direct Walmart contractor comes on site, do they need to produce a
WV form for their workers
-Yes
-No - correct answer- No
If a worker is removed during an audit, are they allowed back on site?
-yes, if they are work authorized
-no, the auditor removed them for a reason
-yes, they need to work
-workers removed during an audit are not allowed back, or onto another
site unless the auditor verifies the worker is work authorized - correct
answer- workers removed during an audit are not allowed back, or
onto another site unless the auditor verifies the worker is work
authorized
How is the site access monitored
-badges
-access point check-in/check-out
-daily site walks
-all of the above - correct answer- all of the above