PJM Generation Dispatcher PREPARATION
TEST 2026 QUESTIONS AND CORRECT
ANSWERS GRADED A+
● Monitoring LMP may give insights into :
A. system constraints
B. system voltage
C. system frefuency
D. time error. Answer: A. system constraints
● PJM calls for which of the following to recover the ACE so that tie
line schedules are maintained ?
A. IRC ( instantaneous reserve check )
B. synchronized Reserves
C. supplemential reserves
D. minimun generation calculation. Answer: B. synchronized Reserves
● If not cancelled by PJM , the minimum generation alert expires :
A. at the end of the specified light load period
, B. when notified by NERC
C. 12 hours after the alert was issued
D. after a 24 hour period. Answer: A. at the end of the specified light
load period
● When PJM declares a hot weather alert , the generation dispatcher
should
1. determine if maintenance can be deferred
2. notift transmission operators
3. notify all generating stations and key personnel
4. direct all generating stations to reduce output
A. 1 and 2 only
B. 1 and 3 only
C. 2 and 4 only
D. 3 and 4 only. Answer: B. 1 and 3 only
1. determine if maintenance can be deferred
3. notify all generating stations and key personnel
● During system restoration, the two categories of reserves are :
TEST 2026 QUESTIONS AND CORRECT
ANSWERS GRADED A+
● Monitoring LMP may give insights into :
A. system constraints
B. system voltage
C. system frefuency
D. time error. Answer: A. system constraints
● PJM calls for which of the following to recover the ACE so that tie
line schedules are maintained ?
A. IRC ( instantaneous reserve check )
B. synchronized Reserves
C. supplemential reserves
D. minimun generation calculation. Answer: B. synchronized Reserves
● If not cancelled by PJM , the minimum generation alert expires :
A. at the end of the specified light load period
, B. when notified by NERC
C. 12 hours after the alert was issued
D. after a 24 hour period. Answer: A. at the end of the specified light
load period
● When PJM declares a hot weather alert , the generation dispatcher
should
1. determine if maintenance can be deferred
2. notift transmission operators
3. notify all generating stations and key personnel
4. direct all generating stations to reduce output
A. 1 and 2 only
B. 1 and 3 only
C. 2 and 4 only
D. 3 and 4 only. Answer: B. 1 and 3 only
1. determine if maintenance can be deferred
3. notify all generating stations and key personnel
● During system restoration, the two categories of reserves are :