ICC SOILS PACKAGED COMPREHENSIVE STUDY GUIDE
2026 FULL QUESTIONS AND SOLUTIONS GRADED A+
● Depending upon the jurisdiction, the SI is required to send their final report to the BO and....
Answer: The DP in responsible charge
● Duties of a special inspector include:. Answer: Review approved plans and specifications
for SI requirements Inspect work for compliance with building department approved plans
Notify in writing a report to be seen by BO and EofRecord of unresolved deviations
● When reporting Non-Conforming Items, all of the following items must be reported:.
Answer: Name and title of each individual notified Reference to applicable detail of approved
plans, job specifications or code Resolution or corrective action taken
● The responsibility of ensuring that day to day work is covered by inspections falls on....
Answer: The Contractor
● When the SI arrives on-site, they should notify the.... Answer: Contractor
● Who issues final acceptance of a building. Answer: The Building Official (BO)
● Whose responsibility is it to monitor the special inspection activities?. Answer: The Building
Official (BO)
● Special Inspection reports should contain all of the following:. Answer: Location and details
of reinforcement inspections Names of individuals notified on-site regarding areas of work
Changes authorized by the DP in responsible charge NO ASTMs
● Who is responsible for approving the special inspection program?. Answer: The Building
Official (BO)
● The responsibilities of the special inspection agency are all of the following:. Answer:
Review approved plans and specifications Write daily reports Report non-conforming items
● The special inspection agency does not need to. Answer: Prepare special inspection
program
● Who does the special inspector notify first if there is a non-conforming item?. Answer: The
Contractor
2026 FULL QUESTIONS AND SOLUTIONS GRADED A+
● Depending upon the jurisdiction, the SI is required to send their final report to the BO and....
Answer: The DP in responsible charge
● Duties of a special inspector include:. Answer: Review approved plans and specifications
for SI requirements Inspect work for compliance with building department approved plans
Notify in writing a report to be seen by BO and EofRecord of unresolved deviations
● When reporting Non-Conforming Items, all of the following items must be reported:.
Answer: Name and title of each individual notified Reference to applicable detail of approved
plans, job specifications or code Resolution or corrective action taken
● The responsibility of ensuring that day to day work is covered by inspections falls on....
Answer: The Contractor
● When the SI arrives on-site, they should notify the.... Answer: Contractor
● Who issues final acceptance of a building. Answer: The Building Official (BO)
● Whose responsibility is it to monitor the special inspection activities?. Answer: The Building
Official (BO)
● Special Inspection reports should contain all of the following:. Answer: Location and details
of reinforcement inspections Names of individuals notified on-site regarding areas of work
Changes authorized by the DP in responsible charge NO ASTMs
● Who is responsible for approving the special inspection program?. Answer: The Building
Official (BO)
● The responsibilities of the special inspection agency are all of the following:. Answer:
Review approved plans and specifications Write daily reports Report non-conforming items
● The special inspection agency does not need to. Answer: Prepare special inspection
program
● Who does the special inspector notify first if there is a non-conforming item?. Answer: The
Contractor