CON 216 LEGAL CONSIDERATIONS IN CONTRACTING EXAM QUESTIONS ANSWERED CORRECTLY LATEST UPDATE 2026

Beoordeling
-
Verkocht
-
Pagina's
6
Cijfer
A+
Geüpload op
25-03-2026
Geschreven in
2025/2026

CON 216 LEGAL CONSIDERATIONS IN CONTRACTING EXAM QUESTIONS ANSWERED CORRECTLY LATEST UPDATE 2026 Acme Corporation submits an initiaAcme Corporation submits an initial proposal to perform maintenance on target drone aircraft at NAS DESERT VISTA. During discussions, the contracting officer notes that Acme's price calculations are based on the premise that Acme will hire mechanics at the labor rates contained in the Department of Labor (DOL) wage determination. The contracting officer notes that Acme already has a contract to provide aircraft maintenance at NAS DESERT VISTA and that the unionized mechanics working under that contract already receive wages higher than the DOL prevailing rate. The contracting officer questions whether Acme will be able to pay new employees less than the wages already being paid to current employees. Acme's project manager concedes it could be a problem and reluctantly agrees to recalculate Acme's price, but complains that "we might lose the contract because of this." Acme's final proposal revision increases the propo - Answers The protest will be dismissed as untimely, because Acme was aware of this ground of protest before submitting the final proposal revision and therefore had to file the protest prior to that time. You have a disagreement with the contractor over the meaning and requirements of a very detailed technical specification. Government experts are adamant that the spec means one thing, while the contractor's technical personnel insists the spec must be read their way. Several meetings have been held between Government and contractor personnel attempting to resolve the specification interpretation issue. The meetings have been friendly, cordial and open, but the parties are no closer to resolving the dispute. Despite lengthy, detailed technical discussions between the parties, the experts on both sides are still convinced that they are right and the other side is mistaken. Which ADR technique would give the best chance for resolving the impasse? - Answers Arbitration using a subject matter expert respected by both sides to render an informed decision based on the merits. Your contractor has completed all deliveries two weeks ago. During contract performance, you have been paying the contractor through an assignment of claims. He is now asking to be released from the assignment of claims since contract performance has been completed. As the Contracting Officer, what should you do? - Answers Require the contractor to file a written notice of release with an original copy of the release of assignment instrument. What party fits the GAO "interested party" definition and therefore can file a protest to an agency procurement? - Answers An agency tender official under an A-76 competition Delta Corp is awarded a FAR Part 12 commercial item contract for 100 television sets to be installed in a new Navy Bachelor Officer Quarters. FAR Clause 52.212-4 is included in the contract and has not been tailored. The sets are delivered and installed two days after acceptance. At that time, it is discovered that 10 of the television sets do not work. The Contracting Officer has the right to issue a letter revoking acceptance of those ten television sets and demanding replacements. - Answers TRUE Which method is used to resolve disputed facts to determine the amount of an equitable adjustment when the contractor is clearly entitled to an equitable adjustment (clear proof of injury) and sufficient evidence exists for a fair approximation of the amount of the adjustment (damages)? - Answers Total cost method Sluggish Corporation Inc. receives an RFP which contains a design specification for a piece of equipment to be manufactured by the winning offeror. Upon review of the specification, the President, Mr. Tortoise, concludes that the specification is "restrictive", in that the specification contains detailed technical requirements that appear to have been taken directly from the descriptive literature of a product manufactured by the Hare Corporation. Mr. Tortoise chooses not to submit an offer. Two months later, after the due date for proposals but before the time for contract award, Mr. Tortoise files a protest at GAO, alleging the RFP specification was restrictive. GAO will most probably: - Answers Dismiss the protest as untimely. Which protest PARTICIPANT reviews the agency's action to ensure that the agency acted in accordance with law? - Answers Government Accountability Office The Contracting Officer's written action on a claim is referred to as a - Answers Contracting Officer's Final Decision. Your contractor has completed all deliveries two weeks ago. During contract performance, you have been paying the contractor through an assignment of claims. He is now asking to be released from the assignment of claims since contract performance has been completed. As the Contracting Officer, what should you do? - Answers Require the contractor to file a written notice of release with an original copy of the release of assignment instrument. Which is correct about an assignment of claims? - Answers An assignment of claims is used to help contractors obtain private financing for a Government contract. Which of the following statements about Common Law Orders of Precedence is incorrect? - Answers Preprinted terms control over handwritten terms. Which protest forum involves a formal structure for filing and will result in a recommendation to the procurement office? - Answers Government Accountability Office Which protest PARTICIPANT is likely to schedule a hearing to resolve issues raised in a protest? - Answers Government Accountability Office Who decides which forum in which to file a timely protest? - Answers Protestor Which statement is true about assignment of claims? - Answers It denotes an agreement between the contractor and financial institution. Which protest PARTICIPANT examines the protest to ensure that it is timely, identifies the basis for the protest, and renders a written decision with factual detail explaining the decision? - Answers Contracting Agency (Officer) Which is the least preferred method for calculating the equitable adjustment? [Distinguish between the methods used to calculate an equitable adjustment] - Answers Total Cost Method Which of the following statements is not accurate regarding disputes and appeals? - Answers The Government's policy is to try to resolve all contractual issues in controversy by mutual agreement at the Head of the contracting agency (HCA) level. You have received a timely letter of protest from an interested party for a contract awarded for base maintenance. You sought legal advice and need to render a decision. Considering the steps in a protest process, which action should you take? - Answers Try to resolve the protest at your level within 35 days and issue a written decision to the protestor. You have elected to use conciliation to resolve a dispute with a contractor. Which of the following is true about this ADR technique? [Distinguish between the disputes resolution techniques] - Answers This ADR technique seeks to restore damaged relationships between parties by bringing them together, clarifying perceptions, and pointing out misconceptions. A claim must be certified when: - Answers Exceeds $100,000.00 (not the correct language, but FAR 32.207 is where the information is) The Air Force Contracted to purchase a quantity of portable electric hand drills. Because the drill was a commercial item, the contract contained the provisions found in FAR 52.212-4, Contract Terms and Conditions - Commercial Items. When the contractor delivered the drills, the Government issued a written acceptance and distributed the drills to the field, without inspecting them. Air Force civil engineering personnel soon found that the drills, in normal use, overheated and burned out their batteries prematurely due to a defect. In using the drill, the government did not substantially change it conditions. What can the Government do to remedy the situation? - Answers The government may require repair or replacement of the drills. The Navy competitively awards a firm fixed price contract for manufacture and delivery of 100 specially designed radios, for use onboard Navy vessels. These radios are not commercial items; they are built to a design specification provided by the government. The contract contains the Changes clause for fixed price supply and service contracts, FAR 52.243-1. Two months into contract performance, the requiring activity informs the contracting officer that it will need an additional 25 radios. The contracting officer unilaterally issues a change pursuant to the changes clause to increase the contract quantity from 100 to 125. Is this a proper action? - Answers Yes, because the change was reasonably foreseeable at the time of contract information. All of the following conditions must be met before the contracting officer may acknowledge the assignment of claims except the - Answers FAR 32.802 Conditions Able contractors has just be debriefed after losing a Government contract. Based upon their product knowledge and knowledge of their competitor's products, Able believes that their offer represented the best value for the Government and the source selection must not have been properly conducted. The information presented at the debrief only reinforces his determination to file a protest. As he leaves, he tells the contracting officer You'll be hearing from my attorney! At this juncture, the contracting offer's best action would be to: - Answers Invite the contractor to have his attorney present at any protest to the agency first. (Basically it is best to start with agency) Which is correct about an assignment of claims? - Answers An assignment of claims is used to help contractors obtain private financing for a Government contract. Which of the following parties would not be considered an "Interested Party" as defined by the FAR? - Answers A company who did not submit a bid and would not receive the award even if its protest was sustained. The government awards a contract to Acme under FAR part 12 to procure 240 chairs and 40 tables from a commercial source. The contract specifies a delivery date of January 15th and the place of delivery is Building 450 of the Naval Station. On January 10th, the contracting officer issues a unilateral change order pursuant to the contract's changes clause, changing the place of delivery to Building 10 of the Naval Submarine Base, which is located 10 miles away from the originally designated site of delivery. This charge order is: - Answers Invalid, because this change should be a bilateral change agreed to by the contractor. Which alternative disputes resolution procedure involves a neutral third party who listens to the issues from both parties and conducts an interested-based negotiation to resolve the contract issues? - Answers Mediation Which method is used to resolve disputed facts to determine the amount of an equitable adjustment when the contractor is clearly entitled to an adjustment (clear proof of injury) and sufficient evidence exists for a fair approximation of the amount of the adjustment (damages)? Jury Verdict (7.2) - Answers Jury Verdict (7.2) What is a complaint? - Answers A legal pleading that sets forth the factual and legal basis for a contractor's claim You have a $1200 contract for 15 desks at $80 per unit. Your contractor has made delivery on 60% of the desks ordered. Up until now, he has been receiving payments for supplies delivered to his main office. He is now requesting that payment for the balance of the desks to be delivered. Be assigned to his bank. You, as the Contracting Officer, on the contract must decide if his is permissible at this point in time. An assignment of claims is permissible in this situation. - Answers False A co-worker retired recently. You have been given many of her contracts to administer. One of these is a contract to replace the roofs on several Government building in the area. As you start going through the stack of mail that she had, you find a FEDEX package containing a letter from the roofing contractor. In the letter the contractor states that the COR on the project had instructed him to make a change to a specification of the roofing materials to withstand an approaching hurricane forecasted to hit within days. Due to the impending hurricane, the contactor stated that if he did not hear back immediately, he would proceed with the COR's requests. What type of contract change occurred? - Answers Constructive Change (6.4)l proposal to perform maintenance on target drone aircraft at NAS DESERT VISTA. During discussions, the contracting officer notes that Acme's price calculations are based on the premise that Acme will hire mechanics at the labor rates contained in the Department

Meer zien Lees minder
Instelling
CON 216 LEGAL CONSIDERATIONS IN CONTRACTING
Vak
CON 216 LEGAL CONSIDERATIONS IN CONTRACTING

Voorbeeld van de inhoud

CON 216 LEGAL CONSIDERATIONS IN CONTRACTING EXAM QUESTIONS ANSWERED CORRECTLY
LATEST UPDATE 2026

Acme Corporation submits an initiaAcme Corporation submits an initial proposal to perform
maintenance on target drone aircraft at NAS DESERT VISTA. During discussions, the contracting officer
notes that Acme's price calculations are based on the premise that Acme will hire mechanics at the
labor rates contained in the Department of Labor (DOL) wage determination. The contracting officer
notes that Acme already has a contract to provide aircraft maintenance at NAS DESERT VISTA and that
the unionized mechanics working under that contract already receive wages higher than the DOL
prevailing rate. The contracting officer questions whether Acme will be able to pay new employees
less than the wages already being paid to current employees. Acme's project manager concedes it
could be a problem and reluctantly agrees to recalculate Acme's price, but complains that "we might
lose the contract because of this." Acme's final proposal revision increases the propo - Answers The
protest will be dismissed as untimely, because Acme was aware of this ground of protest before
submitting the final proposal revision and therefore had to file the protest prior to that time.
You have a disagreement with the contractor over the meaning and requirements of a very detailed
technical specification. Government experts are adamant that the spec means one thing, while the
contractor's technical personnel insists the spec must be read their way. Several meetings have been
held between Government and contractor personnel attempting to resolve the specification
interpretation issue. The meetings have been friendly, cordial and open, but the parties are no closer
to resolving the dispute. Despite lengthy, detailed technical discussions between the parties, the
experts on both sides are still convinced that they are right and the other side is mistaken. Which ADR
technique would give the best chance for resolving the impasse? - Answers Arbitration using a
subject matter expert respected by both sides to render an informed decision based on the merits.
Your contractor has completed all deliveries two weeks ago. During contract performance, you have
been paying the contractor through an assignment of claims. He is now asking to be released from the
assignment of claims since contract performance has been completed. As the Contracting Officer,
what should you do? - Answers Require the contractor to file a written notice of release with an
original copy of the release of assignment instrument.
What party fits the GAO "interested party" definition and therefore can file a protest to an agency
procurement? - Answers An agency tender official under an A-76 competition
Delta Corp is awarded a FAR Part 12 commercial item contract for 100 television sets to be installed in
a new Navy Bachelor Officer Quarters. FAR Clause 52.212-4 is included in the contract and has not
been tailored. The sets are delivered and installed two days after acceptance. At that time, it is
discovered that 10 of the television sets do not work. The Contracting Officer has the right to issue a
letter revoking acceptance of those ten television sets and demanding replacements. - Answers TRUE
Which method is used to resolve disputed facts to determine the amount of an equitable adjustment
when the contractor is clearly entitled to an equitable adjustment (clear proof of injury) and sufficient
evidence exists for a fair approximation of the amount of the adjustment (damages)? - Answers Total
cost method
Sluggish Corporation Inc. receives an RFP which contains a design specification for a piece of
equipment to be manufactured by the winning offeror. Upon review of the specification, the
President, Mr. Tortoise, concludes that the specification is "restrictive", in that the specification
contains detailed technical requirements that appear to have been taken directly from the descriptive
literature of a product manufactured by the Hare Corporation. Mr. Tortoise chooses not to submit an
offer. Two months later, after the due date for proposals but before the time for contract award, Mr.
Tortoise files a protest at GAO, alleging the RFP specification was restrictive. GAO will most probably: -
Answers Dismiss the protest as untimely.
Which protest PARTICIPANT reviews the agency's action to ensure that the agency acted in
accordance with law? - Answers Government Accountability Office
The Contracting Officer's written action on a claim is referred to as a - Answers Contracting Officer's
Final Decision.
Your contractor has completed all deliveries two weeks ago. During contract performance, you have
been paying the contractor through an assignment of claims. He is now asking to be released from the
assignment of claims since contract performance has been completed. As the Contracting Officer,
what should you do? - Answers Require the contractor to file a written notice of release with an
original copy of the release of assignment instrument.

, Which is correct about an assignment of claims? - Answers An assignment of claims is used to help
contractors obtain private financing for a Government contract.
Which of the following statements about Common Law Orders of Precedence is incorrect? - Answers
Preprinted terms control over handwritten terms.
Which protest forum involves a formal structure for filing and will result in a recommendation to the
procurement office? - Answers Government Accountability Office
Which protest PARTICIPANT is likely to schedule a hearing to resolve issues raised in a protest? -
Answers Government Accountability Office
Who decides which forum in which to file a timely protest? - Answers Protestor
Which statement is true about assignment of claims? - Answers It denotes an agreement between
the contractor and financial institution.
Which protest PARTICIPANT examines the protest to ensure that it is timely, identifies the basis for
the protest, and renders a written decision with factual detail explaining the decision? - Answers
Contracting Agency (Officer)
Which is the least preferred method for calculating the equitable adjustment? [Distinguish between
the methods used to calculate an equitable adjustment] - Answers Total Cost Method
Which of the following statements is not accurate regarding disputes and appeals? - Answers The
Government's policy is to try to resolve all contractual issues in controversy by mutual agreement at
the Head of the contracting agency (HCA) level.
You have received a timely letter of protest from an interested party for a contract awarded for base
maintenance. You sought legal advice and need to render a decision. Considering the steps in a
protest process, which action should you take? - Answers Try to resolve the protest at your level
within 35 days and issue a written decision to the protestor.
You have elected to use conciliation to resolve a dispute with a contractor. Which of the following is
true about this ADR technique? [Distinguish between the disputes resolution techniques] - Answers
This ADR technique seeks to restore damaged relationships between parties by bringing them
together, clarifying perceptions, and pointing out misconceptions.
A claim must be certified when: - Answers Exceeds $100,000.00 (not the correct language, but FAR
32.207 is where the information is)
The Air Force Contracted to purchase a quantity of portable electric hand drills. Because the drill was
a commercial item, the contract contained the provisions found in FAR 52.212-4, Contract Terms and
Conditions - Commercial Items. When the contractor delivered the drills, the Government issued a
written acceptance and distributed the drills to the field, without inspecting them. Air Force civil
engineering personnel soon found that the drills, in normal use, overheated and burned out their
batteries prematurely due to a defect. In using the drill, the government did not substantially change
it conditions. What can the Government do to remedy the situation? - Answers The government may
require repair or replacement of the drills.
The Navy competitively awards a firm fixed price contract for manufacture and delivery of 100
specially designed radios, for use onboard Navy vessels. These radios are not commercial items; they
are built to a design specification provided by the government. The contract contains the Changes
clause for fixed price supply and service contracts, FAR 52.243-1. Two months into contract
performance, the requiring activity informs the contracting officer that it will need an additional 25
radios. The contracting officer unilaterally issues a change pursuant to the changes clause to increase
the contract quantity from 100 to 125. Is this a proper action? - Answers Yes, because the change was
reasonably foreseeable at the time of contract information.
All of the following conditions must be met before the contracting officer may acknowledge the
assignment of claims except the - Answers FAR 32.802 Conditions
Able contractors has just be debriefed after losing a Government contract. Based upon their product
knowledge and knowledge of their competitor's products, Able believes that their offer represented
the best value for the Government and the source selection must not have been properly conducted.
The information presented at the debrief only reinforces his determination to file a protest. As he
leaves, he tells the contracting officer You'll be hearing from my attorney! At this juncture, the
contracting offer's best action would be to: - Answers Invite the contractor to have his attorney
present at any protest to the agency first. (Basically it is best to start with agency)
Which is correct about an assignment of claims? - Answers An assignment of claims is used to help
contractors obtain private financing for a Government contract.

Geschreven voor

Instelling
CON 216 LEGAL CONSIDERATIONS IN CONTRACTING
Vak
CON 216 LEGAL CONSIDERATIONS IN CONTRACTING

Documentinformatie

Geüpload op
25 maart 2026
Aantal pagina's
6
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

€10,18
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
joshuawesonga22 Liberty University
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
99
Lid sinds
1 jaar
Aantal volgers
1
Documenten
14163
Laatst verkocht
17 uur geleden
Tutor Wes

Hi there! I'm Tutor Wes, a dedicated tutor with a passion for sharing knowledge and helping others succeed academically. All my notes are carefully organized, detailed, and easy to understand. Whether you're preparing for exams, catching up on lectures, or looking for clear summaries, you'll find useful study materials here. Let’s succeed together!

3,9

9 beoordelingen

5
4
4
1
3
3
2
1
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen