Based on the guide quantity of 100 CY on a bid document for rock excavation, a
contractor bid a unit price of $20/CY. If the owner's representative determined
that the contractor excavated 85 CY of rock during construction, how much will
the contractor get paid?
(a). $2000
(b). $1700
(c). $300
(d). $1800
(b)
Which of the following documents are included in the bid package?
I. Proposal Form
II. Special Conditions
III. Technical Specifications
IV. General Conditions
V. Bid Bond
,(a). I, II, and III
(b). II, III, and IV
(c). I, II, IV, and V
(d). I, II, III, and IV
(d)
The document requested by the owner as a protection against the risk of the
contractor not accepting the job once awarded the project is
(a). Insurance
(b). Performance Bond
(c). Bid Bond
(d). Payment Bond
(c)
Which of the following would not be considered an excusable delay?
(a). Labor Strikes
(b). Review process delays
(c). A hurricane closing a port delaying delivery of materials
(d). Death of a contractor
(b)
, The typically 30-90 days period after the bid opening where the contractor is
bound by their bid is called
(a). Acceptance period
(b). Bid period
(c). Anxiety period
(d). Risk period
(a)
The procedure that allows a contractor to propose changes to the design with the
approval of the designer to save time and/or money is called
(a). Process Engineering
(b). Value Engineering
(c). Design build engineering
(d). Cost engineering
(b)
Which of the following documents determines the zero day of the project for
scheduling purposes?
(a). Proposal Form
(b). Formal contract
(c). Notice to bidders