Working on an energized lattice tower requires emergency response consistent with the associated
hazards. What is NOT required as part of the emergency planning: - - ANSWER✔ Daily practice
of tower rescue method.
Working on an energized lattice tower requires emergency response consistent with the associated
hazards, including: - - ANSWER✔ 1. A means to contact the operating authority to de-energize
the circuit.
2. Rescue equipment readily available to quickly and safely lower the worker.
3. Regular rescue practices on tower rescue at an appropriate frequency.
Z259.14 wooden pole choker devices that are designed and tested to restrict a workers fall distance
under dry, wet, and icy conditions are classified as: - - ANSWER✔ Type AB device.
The voltage limits and mechanical strength of a live line tool is best specified by: - - ANSWER✔
The manufacturers requirements.
, 2
Live line tools can be modified to meet the needs of the work. What is NOT an acceptable strategy
for tool modification: - - ANSWER✔ A utility worker has evaluated the tool modification and
approved the change.
Live line tools can be modified to meet the needs of the work. Acceptable strategies for tool
modification include: - - ANSWER✔ 1. Changes to the tool do not violate other applicable
standards.
2. The tool has been inspected and tested by a professional engineer.
3. The tool modification was approved by an engineer using applicable standards.
Insulating hot rope (live line rope) is tested in accordance to ASTM F1701. The purpose of this
test is to: - - ANSWER✔ Determine the current leakage under dry and wet rope conditions.
Live line rigid cover in compliance with CAN/ULC-61229 includes the following pieces or
protective insulating equipment EXCEPT for: - - ANSWER✔ Insulating line hose.
Live line rigid cover in compliance with CAN/ULC-61229 includes the following pieces or
protective insulating equipment, including: - - ANSWER✔ 1. Conductor cover (air guard).
2. Pole guard.
3. Switch and insulator shields.
This statement is true, regarding the application of cover-up on energized high voltage lines: - -
ANSWER✔ If left overnight, a visual inspection must be performed at minimum prior to use.
, 3
What is NOT a fundamental principle of live line work tools: - - ANSWER✔ Valid lab test dates
provide sufficient verification of tool dielectric properties.
As per CAN/ULC S801, on an electrical distribution overhead utility line circuit, verification of
voltage absence can be achieved by: - - ANSWER✔ Using an approved voltage detector.
Isolation and tagging (no locks) is acceptable on an overhead distribution circuit under some of
the following conditions, EXCEPT for: - - ANSWER✔ The isolation can be operated from the
ground directly at the base of a structure.
Isolation and tagging (no locks) is acceptable for an overhead distribution circuit under some of
the following conditions: - - ANSWER✔ 1. The isolation point is a physical and visual like a line
cut or riser removed.
2. The isolation point can only be operated by the operating authority or qualified worker.
3. The isolation point is protected from unauthorized access such as vertical height spacing.
Consider that a circuit has been isolated, tagged and grounded. workers returning the next day
must: - - ANSWER✔ Visually check grounds to verify they are in good order, secure and test for