A county government wants one entity accountable for both design
errors and construction defects. Which delivery method best satisfies
this goal?
A. Multiple Prime
B. Design-Bid-Build
C. Design-Build
D. Agency CM - Correct Answer - C. Design-Build
Design-build provides single-point responsibility for design and
construction.
A project team identifies steel procurement delays threatening
occupancy dates. What should occur first?
A. Stop all field work
B. Expedite long-lead procurement
C. Redesign the structure
D. Remove schedule milestones - Correct Answer - B. Expedite long-
lead procurement
Early procurement minimizes critical-path delays.
pg. 1
,An owner prioritizes innovation over lowest cost. Which selection
method is best?
A. Hard bid
B. Best-value procurement
C. Low responsive bid
D. Reverse auction - Correct Answer - B. Best-value procurement
Best-value considers technical strength and innovation.
A design-builder receives incomplete utility data from the owner. Which
clause becomes most important?
A. Force majeure
B. Differing site conditions
C. Warranty waiver
D. Liquidated damages - Correct Answer - B. Differing site conditions
The clause addresses unforeseen physical conditions.
Which practice best reduces BIM coordination conflicts?
A. Independent modeling
B. Weekly clash reviews
C. Delayed coordination
D. Separate schedules - Correct Answer - B. Weekly clash reviews
Frequent reviews identify conflicts early.
An owner keeps changing room layouts after pricing is established.
What is the best control method?
pg. 2
,A. Verbal approvals
B. Scope freeze only
C. Formal change management
D. Reduced inspections - Correct Answer - C. Formal change
management
Structured change control protects budget and schedule.
A design-build team wants faster project delivery. Which strategy helps
most?
A. Sequential construction
B. Early trade involvement
C. Delayed procurement
D. Independent scheduling - Correct Answer - B. Early trade
involvement
Early collaboration improves efficiency and sequencing.
A public agency wants fair proposal evaluations. What is most
important?
A. Confidential scoring changes
B. Clear evaluation criteria
C. Lowest design fee
D. Informal interviews only - Correct Answer - B. Clear evaluation
criteria
Transparency improves procurement defensibility.
Which document defines owner performance expectations?
pg. 3
, A. Daily reports
B. Subcontract agreements
C. Owner’s criteria document
D. Punch list - Correct Answer - C. Owner’s criteria document
The criteria document establishes project requirements.
An owner wants to improve assigning risk to the party best able to
manage it during a complex public infrastructure project. Which
approach would best support this objective?
A. Waiting until construction completion to coordinate trades
B. Establishing performance requirements early
C. Eliminating owner reviews
D. Avoiding multidisciplinary meetings - Correct Answer - B.
Establishing performance requirements early
Clear performance expectations established early support better
alignment and efficient delivery.
Which project delivery decision most directly improves confirming
budget and scope feasibility?
A. Strict separation of designer and constructor responsibilities
B. Qualifications-focused team selection
C. Delayed constructability reviews
D. Independent risk management systems - Correct Answer - B.
Qualifications-focused team selection
Qualifications-focused procurement helps owners select capable teams
that align with project goals.