What is the purpose of annual operator system restoration training?
ANSWERS: To assure proper execution of its restoration plan
Name 4 things required in annual operator system restoration training:
ANSWERS: System restoration plan including coordination with RC
and GO; Restoration Priorities; Building of cranking paths;
Synchronizng
How often and how much training is required for field switching
personnel who are included in the system restoration plan?
ANSWERS: Minimum 2 hrs every 2 years
, When must a TO or GO participate in RC restoration drills, exercises
or simulations?
ANSWERS: As requested by the RC
What is a Blackstart Resource Agreement?
ANSWERS: This is an agreement between a TO and GO that
includes the terms and conditions of the use of the Blackstart
Unit; e.g. procedures, protocols, testing requirements
What is required by each GO for their Blackstart Resources?
ANSWERS: Documented procuedures for starting each resource and
energizing a bus
What 9 things are included in the RC restoration plan?
ANSWERS:
High level strategy; Operating process to restore
Interconnection;
coordination elements between TO restoration plans;
elements between RC plans; criteria and condition for
reestablishing interconnections (TO-TO in the RC; TO-TO
w/ other RC; w/ Other RC); Reporting requirements;
Criteria for info sharing w/ neighboring RC and TO/BA in
its area; RC as main
contact for all parties; Criteria to transfer operations &
authority back to BA
,Who must a GO notify if a Blackstart Resource ability to perform its
function is changed?
ANSWERS: The TO who holds the agreement
What is the time requirement for a GO to notify its TO when a Blackstart
Resource capabilities are compromised?
ANSWERS: 24 Hours
Who is required to perform the agreed upon testing of a Blackstart
Resource?
ANSWERS: The GO
What minimum information should be recorded for a Blackstart
Resource test?
ANSWERS: Name of Resource, unit tested, date of test, duration of
test, time required to start, and any test requirements not met
If requested by a TO or RC, when must Blackstart Resource test results
be produced?
ANSWERS: The GO has 30 days to provide test results to its TO or RC
, How much time and how frequently must a GO train its personnel
on starting a Blackstart Resource and energizing a bus?
ANSWERS: 2 hours every 2 years minimum
What two things must be included in the GO Blackstart Resource
biannual training?
ANSWERS: The system restoration plan including coordination with
the TO; The procedures associated with the Blackstart Resource
Agreement
What must each RC have in regard to restoration?
ANSWERS: Each RC is required to have an RC Area Restoration Plan.
Name the three things covered in the RC Area Restoration Plan?
ANSWERS: Blackstart Resources used to re-energize a shut down area
of the BES;
separation has occurred between neighboring RC; An energized
island has been formed on the BES
When does the RC exit the Restoration plan?
ANSWERS: All TO are interconnected its RC area is connected to all
neighboring RC