the ____________________
body and tongue
trimmer or jack studs strengthen the sides of an opening
and bear the direct weight of the
header
,a concrete block measures _________W x __________ H x
____________L
8x8x16
true or false: you should always install standing trim first as
opposed to installing the running trim first
true
,when working in damp or wet coactions workers should
plug tools into _____________ receptacles
GFCI
these tools attach to a framing square to assist in laying
out rafters and stringers
stair gauges
, when installing siding which of the following is installed
last
siding panels
true or false: dull tools are just as dangerous as sharp ones
true