WGU C722 Project Management OA Exam 2026/2027 – Actual Questions with Verified Correct Answers & Expert Solutions

Beoordeling
-
Verkocht
-
Pagina's
110
Cijfer
A
Geüpload op
25-05-2026
Geschreven in
2025/2026

WGU C722 Project Management OA Exam 2026/2027 – Actual Questions with Verified Correct Answers & Expert Solutions

Instelling
WGU C722
Vak
WGU C722

Voorbeeld van de inhoud

1|Page



WGU C722 Project Management OA Exam 2026/2027 –
Actual Questions with Verified Correct Answers &
Expert Solutions
A firm begins its strategic business initiative of developing a new
business model that will allow the firm to deliver an efficient, tailored
service to its customers. To accomplish this, the firm initiates a business
management project. Which aspect of project management applies to
this firm's project? ......ANSWER......Interdependent Tasks


A firm begins its strategic business initiative of developing a new
business model to enhance its competitiveness. What can be identified
as a strategic business initiative for this firm?
......ANSWER......Improvement in product design


A firm begins a strategic business initiative of developing a new
business model that will allow the firm to deliver an efficient, tailored
service to its customers. ......ANSWER......Project sponsor


Which group is included in the five process groups?
......ANSWER......Closing process group


What does PRINCE2 stand for? ......ANSWER......PRojects IN a
Controlled Environment




pg. 1

,2|Page


Which PMBOK process group is described as the delivery part of project
management where the main activity happens?
......ANSWER......Executing


Which advantage does the functional (departmentalized) organizational
structure provide for a firm with multiple projects?
......ANSWER......Lines of authority are clear.


Which two organizations are examples of organizations with the
functional organizational structure? ......ANSWER......(1) The U.S.
Department of State and (2) The U.S Department of Energy


An organization expects to use a project management office (PMO) to
support multiple projects that will be implemented within a projectized
organizational structure. Which implied effect is a benefit to this
organization? ......ANSWER......Project team members gain access to
historical data from other projects.


Regardless of the organizational structure used to manage a project, an
organization elects to use a project management office (PMO). Which
benefit will this organization gain? ......ANSWER......Projects will
coordinate resource usage by monitoring the status of shared
resources.


During a certain project phase, specific blueprints are drawn and
approved, materials and labor costs are estimated, prototypes are
created, and work activities and tasks are identified. Also, quality

pg. 2

,3|Page


expectations, measurements, and costs are defined. During which
project phase do these activities occur? ......ANSWER......Planning


Place the project activities in order of occurrence from first (1) to last
(5). ......ANSWER......(1) Collecting customer requirements (2)
Developing the work breakdown structure (3) Working to produce
project deliverables (4) Customers evaluating the project outcomes (5)
Capturing lessons learned


During which life cycle phase is the vast majority of the actual work to
produce the project's deliverables completed?
......ANSWER......Executing


What is the correct term for an intermediate outcome of project work,
such as a signed contract or obtaining a construction permit?
......ANSWER......Deliverable


Which deliverable from a work breakdown structure (WBS) is not
specific enough to measure its completion at project closure?
......ANSWER......User training


The following table shows the Level 1 work breakdown structure (WBS)
for Project A.


WBS ID Description



pg. 3

, 4|Page


0.0 Project A
1.0 Project started
2.0 Feasiblity
3.0 Design
4.0 Development
5.0 Manufacturing
6.0 Distribution
7.0 Project completed
Which approach did the project manager use to structure the WBS?
......ANSWER......Sequence of project phases


For the following collapsed work breakdown structure (WBS) for Project
O, the project manager must complete the scope baseline. In addition
to the WBS, the scope baseline will contain two additional documents.


WBS ID Description
0.0 Project O
1.0 Project started
2.0 Feasibility
3.0 Design
4.0 Development
5.0 Manufacturing
6.0 Distribution


pg. 4

Geschreven voor

Instelling
WGU C722
Vak
WGU C722

Documentinformatie

Geüpload op
25 mei 2026
Aantal pagina's
110
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

€18,01
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
AceExam1 Teachme2-tutor
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
28
Lid sinds
1 jaar
Aantal volgers
1
Documenten
2072
Laatst verkocht
2 dagen geleden

As a tutor, I focus on offering accurate, reliable, and current study materials to support students in their exam preparation and assignments. My goal is to provide the best resources, such as summaries and nursing exam test banks, ensuring that students can buy with confidence. I encourage customers to leave reviews after purchases for quality assurance and to recommend my services to others. Thank you for your support and trust.

3,2

9 beoordelingen

5
4
4
0
3
1
2
2
1
2

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen