QUESTIONS AND CORRECT ANSWERS (VERIFIED
ANSWERS) Q&A 2026|INSTANT DOWNLOAD PDF
1. What is the primary purpose of a general contractor?
A. Design structures only
B. Perform electrical work only
C. Manage and oversee construction projects
D. Approve building codes
Correct Answer: C
Rationale: A general contractor coordinates and supervises all
aspects of construction projects.
2. Which document defines the scope of work in a
construction contract?
A. Blueprint only
B. Scope of Work Statement
C. OSHA report
D. Warranty bond
Correct Answer: B
Rationale: The scope of work outlines all tasks and
responsibilities.
3. What does OSHA primarily regulate?
,A. Building permits
B. Worker safety conditions
C. Tax compliance
D. Material pricing
Correct Answer: B
Rationale: OSHA ensures safe working conditions in
construction sites.
4. Which is the first step in project planning?
A. Hiring subcontractors
B. Site cleanup
C. Feasibility study
D. Pouring foundation
Correct Answer: C
Rationale: Feasibility determines if a project is viable.
5. What type of contract fixes price before work begins?
A. Cost-plus contract
B. Time and materials contract
C. Lump sum contract
D. Unit price contract
Correct Answer: C
Rationale: Lump sum contracts set a fixed total price.
,6. What is a building permit issued for?
A. Hiring workers
B. Approving construction compliance
C. Purchasing materials
D. Financing projects
Correct Answer: B
Rationale: Permits ensure compliance with building codes.
7. Who is responsible for job site safety?
A. Architect
B. Owner only
C. General contractor
D. City inspector only
Correct Answer: C
Rationale: The GC ensures overall site safety compliance.
8. What does “blueprint” represent?
A. Legal contract
B. Financial report
C. Construction drawings
D. Safety checklist
Correct Answer: C
Rationale: Blueprints are technical drawings of a structure.
, 9. What is a change order?
A. Job termination notice
B. Modification to original contract scope
C. Safety violation report
D. Permit cancellation
Correct Answer: B
Rationale: Change orders modify contract terms.
10. What is the purpose of a subcontractor?
A. Approve permits
B. Perform specialized work
C. Finance project
D. Inspect materials
Correct Answer: B
Rationale: Subcontractors handle specific trades like plumbing
or electrical.
11. What is critical path in project management?
A. Longest sequence of tasks determining project duration
B. Shortest task list
C. Budget summary
D. Safety report