27. A project team that is almost done designing a new construction office building
wishes to achieve option 1 of the EQ Credit—Interior Lighting to get a platinum
certification. To achieve the credit they will:
Give this one a try later!
a. Install LED light bulbs in all fixtures.
b. Install one skylight in every regularly occupied space.
c. Provide individual lighting controls for at least 90% of occupants
d. Provide individual lighting controls for 50% of occupants.
43. a. All materials whose cost can easily be affected by inflation
b. Architectural and engineering fees
c. Fixtures and furniture
d. Landscaping
Give this one a try later!
, While hard costs of building include such things as labor and materials, soft
costs include:
7. a. Generally held at the end of the project
b. The process of bringing in the design team only for focused conversations
c. The process brings together the project team with stakeholders and outside
experts for creative
thinking and collaboration
d. A gathering of LEED APs for a general discussion on sustainability
Give this one a try later!
A charrette is:
93. a. Adds value to products and materials that are produced with renewable
resources
b. Takes away value from products and materials that are not locally produced
c. Adds value to locally produced products and materials
d. Takes away value from products and materials that are produced with fossil fuels
Give this one a try later!
The location valuation factor in the Materials and Resources (MR) category:
41. a. The system that costs $10,000, has a payback of 20 years, has a life expectancy
of 10 years, and will cost $20,000 in maintenance over its lifetime.
b. The system that costs $15,000, has a payback of 10 years, a life expectancy of 14
years, and will cost $17,000 in maintenance over its lifetime.
c. The system that costs $30,000, has a payback of 2 years, a life expectancy of 35
,years, and will cost $10,000 in maintenance over its lifetime.
d. The system that costs $50,000, has a payback of 15 years, a life expectancy of 20
years, and will cost $20,000 in maintenance over its lifetime.
Give this one a try later!
A project team needs to recommend an HVAC system to the owner. Which
of the following options is the best investment over the lifetime of the
HVAC system:
83. a. Suitable for drinking
b. Harvested rainwater
c. Not suitable for drinking
d. Graywater
Give this one a try later!
Potable water is water that is:
90. a. Reduce, reuse, recycle
b. Discovery, implementation, and occupancy
c. Metering, measurement, verification
d. Plan, do, act
Give this one a try later!
The three phases of the integrative process are:
, 9. a. Minimum energy performance
b. Mechanically ventilated spaces
c. Thermal comfort of indoor occupants
d. Naturally ventilated spaces
Give this one a try later!
ASHRAE 55 relates to:
84. a. Protect the interests of company shareholders.
b. Ensure that buildings and communities create value for all stakeholders, not just a
restricted few.
c. Put the environmental needs of the community before those of the shareholders.
d. Ensure that stakeholders create value for all buildings and communities.
Give this one a try later!
The goal of the triple bottom line, in terms of the built environment, is to:
28. Using the building layout, fabric, and form to achieve heat transfer and air
movement through intentional openings in interior spaces is called:
Give this one a try later!
a. Mechanical ventilation
b. Recirculated air
c. Natural ventilation
d. Mixed-mode ventilation
wishes to achieve option 1 of the EQ Credit—Interior Lighting to get a platinum
certification. To achieve the credit they will:
Give this one a try later!
a. Install LED light bulbs in all fixtures.
b. Install one skylight in every regularly occupied space.
c. Provide individual lighting controls for at least 90% of occupants
d. Provide individual lighting controls for 50% of occupants.
43. a. All materials whose cost can easily be affected by inflation
b. Architectural and engineering fees
c. Fixtures and furniture
d. Landscaping
Give this one a try later!
, While hard costs of building include such things as labor and materials, soft
costs include:
7. a. Generally held at the end of the project
b. The process of bringing in the design team only for focused conversations
c. The process brings together the project team with stakeholders and outside
experts for creative
thinking and collaboration
d. A gathering of LEED APs for a general discussion on sustainability
Give this one a try later!
A charrette is:
93. a. Adds value to products and materials that are produced with renewable
resources
b. Takes away value from products and materials that are not locally produced
c. Adds value to locally produced products and materials
d. Takes away value from products and materials that are produced with fossil fuels
Give this one a try later!
The location valuation factor in the Materials and Resources (MR) category:
41. a. The system that costs $10,000, has a payback of 20 years, has a life expectancy
of 10 years, and will cost $20,000 in maintenance over its lifetime.
b. The system that costs $15,000, has a payback of 10 years, a life expectancy of 14
years, and will cost $17,000 in maintenance over its lifetime.
c. The system that costs $30,000, has a payback of 2 years, a life expectancy of 35
,years, and will cost $10,000 in maintenance over its lifetime.
d. The system that costs $50,000, has a payback of 15 years, a life expectancy of 20
years, and will cost $20,000 in maintenance over its lifetime.
Give this one a try later!
A project team needs to recommend an HVAC system to the owner. Which
of the following options is the best investment over the lifetime of the
HVAC system:
83. a. Suitable for drinking
b. Harvested rainwater
c. Not suitable for drinking
d. Graywater
Give this one a try later!
Potable water is water that is:
90. a. Reduce, reuse, recycle
b. Discovery, implementation, and occupancy
c. Metering, measurement, verification
d. Plan, do, act
Give this one a try later!
The three phases of the integrative process are:
, 9. a. Minimum energy performance
b. Mechanically ventilated spaces
c. Thermal comfort of indoor occupants
d. Naturally ventilated spaces
Give this one a try later!
ASHRAE 55 relates to:
84. a. Protect the interests of company shareholders.
b. Ensure that buildings and communities create value for all stakeholders, not just a
restricted few.
c. Put the environmental needs of the community before those of the shareholders.
d. Ensure that stakeholders create value for all buildings and communities.
Give this one a try later!
The goal of the triple bottom line, in terms of the built environment, is to:
28. Using the building layout, fabric, and form to achieve heat transfer and air
movement through intentional openings in interior spaces is called:
Give this one a try later!
a. Mechanical ventilation
b. Recirculated air
c. Natural ventilation
d. Mixed-mode ventilation