T or f A competitive contract can be held up to seven years -
ANSWER ✔✔False five years
T or F you can negotiate on competitive RFP contracts - ANSWER
✔✔False
The report ranking proposals vendors etc. shall be made available to the
public at least 48 hours prior to the governing body awarding contracts -
ANSWER ✔✔True
,Specifications can required form a preapproval or prequalification Of an
equivalent product before submission of bids - ANSWER ✔✔False
under no circumstances should specifications require preapproval or
prequalification
T or F we are not exempt from late fees or interest - ANSWER
✔✔True
Emergencies can require a chain of command and it's written in the
policy and procedure book - ANSWER ✔✔True
For capital improvements a 5% down payment is required and is
financed by bonds and notes - ANSWER ✔✔True
True or false the Q PA can award extraordinary unspecifiable service
contracts - ANSWER ✔✔False the governing body
True or false real property is buildings and grounds not construction -
ANSWER ✔✔True
A business receiving less than 50,000 in public contracts has to file a
report with ELEC - ANSWER ✔✔False a business receiving more
than 50,000 must file
, True or false if you have a contract exceeding 10,000,000 you must
report the proposed award to the office of state Comptroller 30 days prior
to the anticipated award date for approval - ANSWER ✔✔True
True or false contracts equal to or exceeding $5 million shall allow for
value engineering construction change orders to be approved after the
award contract - ANSWER ✔✔True
True or false if the remaining amount exceeds the bed threshold public
betting should take place as soon as possible - ANSWER ✔✔True
True or false if the remaining amount is between 15% and 100% of the
unit bed threshold an additional purchases are required for the current
year only public betting is the only option - ANSWER ✔✔False you
can receive authorization from the governing body or designee To solicit
quotes or publicly bit
If the remaining amount is between 15% and 100% of the units bid
threshold and additional purchases are required for current year and
subsequent year but the total is less than the bed threshold you can get
authorization from the governing body or designee to solicit quotes or
publicly bid - ANSWER ✔✔True