latest 2022 modules tests
LORA - answer Level of Repair Analysis: LORA will ensure that operational readiness
is achieved throughout a system's life cycle in an optimal, least cost fashion. Starting
the LORA process early in a system's development, and continuous evaluation
throughout its life cycle, can ensure LORA influences the systems design and the
maintenance planning by producing an effective support solution.
LORA considers: - answer Cost, performance, schedule, and supportability to aid in
finalizing an effective and supportable design solution.
FTA - answer Fault Tree Analysis: Involves using deductive logic to determine the
possible causes of a defined undesired operational result. It is a top-down failure
analysis of a system that analyzes a series of lower-level events.
RCM - answer Reliability Centered Maintenance (RCM): consists of a systematic
approach of analyzing system/equipment reliability and system safety data to determine
the feasibility and desirability of preventive maintenance activities, to highlight
maintenance problem areas for design review consideration, and to establish the most
effective preventative maintenance program for a system/equipment.
Level of repair Analysis (LORA) - answer The objectives of performing a LORA is to
ensure that operational readiness is achieved throughout a system's life cycle in an
optimal, least cost fashion. Starting the LORA process early in a system's development,
and continuous evaluation throughout its life cycle, can ensure a LORA influences the
systems design and the maintenance planning by producing an effective support
solution.
MTA - answer Maintenance Task Analysis (MTA): The identification of the steps,
spares and materials, tools, support equipment, personnel skill levels as well as any
facility issues that must be considered for a given repair task. Also include in the MTA
are elapsed times required for the performance of each task.
The Four Prime factors that govern system acquisition programs are: - answer Cost,
schedule, performance, and supportability.
Enclosure 6, Section 3 of DoDI 5000.02 requires that the Life-Cycle Sustainment Plan
(LCSP) will: - answer Describe sustainment influences on system design and the
technical, business, and management activities to develop, implement, and deliver a
product support package.
BIT (built in test) - answer Component enables the system to conduct a self-test to
determine if the system is functioning properly.
70-80% of a system's entire cost is during the operation and support (O&S) cycle. -
answer
, ACQ 202 Intermediate Systems Acquisition/ ACQ202 all
latest 2022 modules tests
Reliability defined: - answer How long an item or system will perform its function before
it breaks. The term MTBF is used to quantify and measure reliability and is defined in
the Capability Development Document (CDD).
Reliability is a mandatory Key Systems Attribute (KSA) for: - answer ACAT I programs.
For ACAT II programs and below, the user representative (service sponsor) will
determine applicability.
MTTR (Mean Time To Repair) - answer Used to quantify and measure maintainability.
Material Availability (Am): - answer Is a mandatory Key Performance Parameter (KPP)
and is contained in the Capability Development Document (CDD).
(Am) is defined as: - answer the measure of the percentage of the total inventory of a
system operational cable of performing an assigned mission given material condition.
Reliability, maintainability, and supportability are critical factors in achieving: - answer
maximum Operational Availability (Ao)
The primary purpose of the Future Years Defense Program (FYDP)? - answer Display
the manpower, force structure, and funding of the DoD.
The Planning, Programming, Budgeting and Execution (PPBE) process provides a
process by which the DoD can: - answer Identify the fiscal needs of the services and
decide how to allocate resources.
During the annual PPBE Programming activity, each service and defense agency
submits: - answer Their POM (program objectives memorandum) to the OSD.
What funding policy applies to the procurement appropriations category? - answer Full
Funding
PPBE - answer Is the primary resource allocation process for DoD. The PPBE is an
iterative, calendar-driven process that operates in one year year cycle.
Programming phase - answer Translates planning decisions and OSD programming
guidance into detailed allocation of time-phased resource requirements.
The primary building block in the PPBE process: - answer Future Years Defense
Programming (FYDP)
FYDP - answer It sis the single database that summarizes all forces, funding, and
manpower associated with programs approved by the Secretary of Defense.
The FYDP shows funding requirements for: - answer Five years out into the future