In 2013, the Westgate Construction Company entered into a contract to construct a road for Santa Clara
County for $10,000,000. The road was completed in 2015. Information related to the contract is as
follows:
Westgate uses the percentage-of-completion method of accounting for long-term construction contracts.
Required:
1. Calculate the amount of gross profit to be recognized in each of the three years.
2. Prepare all necessary journal entries for each of the years (credit various accounts for construction
costs incurred).
3. Prepare a partial balance sheet for 2013 and 2014 showing any items related to the contract.
4. Calculate the amount of gross profit to be recognized in each of the three years assuming the following
costs incurred and costs to complete information:
Calculate the amount of gross profit to be recognized in each of the three years assuming the following
costs incurred and costs to complete information:
Answer:
, Requirement 1
2013 2014 2015
Contract price $10,000,000 $10,000,000 $10,000,000
Actual costs to date 2,400,000 6,000,000 8,200,000
Estimated costs to complete 5,600,000 2,000,000 -0-
Total estimated costs 8,000,000 8,000,000 8,200,000
Estimated gross profit (loss)
(actual in 2015) $ 2,000,000 $ 2,000,000 $ 1,800,000
Gross profit (loss) recognition:
2013: $2,400,000
= 30.0% x $2,000,000 = $600,000
$8,000,000
2014: $6,000,000
= 75.0% x $2,000,000 = $1,500,000 – 600,000 = $900,000
$8,000,000
2015: $1,800,000 – 1,500,000 = $300,000
Requirement 2
2013 2014 2015