Study online at https://quizlet.com/_1cw8p8
Contractors Law Exam Ca Practice Test 1 Questions & with
correct Answers ( A+ Graded 100% Verified)2024/2025
1. When is an employee allowed to view their own personnel file?
a. never
b. when they have a court order
c. whenever they wish
d. during employee evaluations: c. when ever they wish
2. As required by the immigration reform act, all employees hired on or after
November 7, 1986 must complete Form ______ to verify their employment
eligibility status. a. I-9
b. W-4
c. US- 99
d. N-14: a. I-9
3. By law, a "hard laborer" may not be younger than _____ years old. a. 14
b. 15
c. 16
d. 17: c. 16 years of age
4. Ms. Gomez applies for a job. Of the following, the only reason an employer may
lawfully deny her employment is: a. she is over 50 years of age
b. she is Hispanic and everyone else is African-American or Caucasian.
c. lifing is involved and she is a woman
d. she has no work experience or Social Security number: d. she has no work
experience or Social Security number
5. A contractor has had a problem with employees stealing tools and equipment
from job sites. When conducting job interviews, may the contractor ask prospective
employees about their arrest records?
a. It is legal to ask prospective employees about arrests not leading to convic-tions.
b. It is not legal to ask prospective employees about arrests not leading to
convictions.
c. It is legal for a private employer to ask about arrests not leading to convic-tions,
but it would not be legal for city or county agencies to ask about such
arrests.
d. It is legal for a private employer to ask about arrests leading to convictions, but it
would not be legal for a federal, state, or local public agency to do so.: b.
, Contractors Law Exam CA Practice Test 1
Study online at https://quizlet.com/_1cw8p8
It is not legal to ask prospective employees about arrests not leading to convictions.
6. Who must sign a joint control addendum to a home improvement contract? a.
contractor only
b. owner and contractor
c. owner, contractor and Notary Public
d. owner, contractor, and joint control officer: d. owner, contractor, and joint control
officer
7. A contractor entered into a home improvement contract for more than $500 with
Mrs. Swenson to remodel her kitchen and bathroom. The contract calls for a down
payment before work is to begin. According to the Business and Professions Code,
how much may the contractor accept from Mrs. Swenson as down payment for the
work?
a. The contractor may accept as much as Mrs. Swenson agrees to pay.
b. The down payment is limited to $1,000 or 10% of the total price, whichever is
less.
c. The contractor may require enough of a down payment to cover the total cost of
materials, but not labor costs.
d. Nothing. The contractor must wait until the work is completed to accept any
payment.: b. The down payment is limited to $1,000 or 10% of the total price,
whichever is less.
8. When should you let an attorney see a construction contract?
a. Before you let your client see the contract.
b. After the contract is prepared, but before you sign it.
c. After the building permit is obtained.
d. After the contract is signed by you and your client.: b. After the contract is
prepared, but before you sign it.
9. If a sales presentation is made in Spanish, the home solicitation contract: a. must
be in Spanish
b. may be in English if the writing is plain and simple
c. must be co-signed by an English-speaking person if the contract is in
English
d. must be translated into English and notarized: a. must be in Spanish
10. A contractor and a homeowner sign a home solicitation contract. If the owner
lawfully cancels the contract, how long does the contractor have to pick up unused
materials that were delivered to the owner's property? a. within 24 hours after
cancellation
, Contractors Law Exam CA Practice Test 1
Study online at https://quizlet.com/_1cw8p8
b. within 10 days after cancellation
c. within 20 days after cancellation
d. It's too late. If the materials are delivered to the property before a notice of
cancellation is received, the materials become the property of the owner.: c.
within 20 days after cancellation
11. Of the following, which is best for determining the number of hours required for
different phases of a project and for making sure the job is on schedule?
a. bar graph and chart
b. cash analysis chart
c. review plans
d. critical path method: d. critical path method
12. Who is responsible for checking the site before the building inspector arrives?
a. contractor
b. owner
c. foreperson
d. architect: a. contractor
13. Who would be held responsible if a contractor completes a project according to
plans and later discovers that there is a building code violation? a. contractor
b. architect
c. both the contractor and the architect
d. owner: c. both the contractor and the architect
14. After a job is completed, the owner decides to have additional work done.
How should the contractor proceed?
a. Write a new contract and ask the owner to sign it.
b. Make an oral agreement with the owner.
c. Do the additional work for free.
d. Get the owner to sign a change order.: a. Write a new contract and ask the owner to
sign it.
15. You have been awarded a job. It requires two days for site preparation and one
day for clean-up. The contract involves two seaparate tasks - one lasting seven days
and the other 10 days. If the two tasks can be done simultaneously, for how many
days do you schedule the job? a. 7 days
b. 13 days
c. 15 days
d. 20 days.: b. 13 days