CMGT 360 EXAM QUESTIONS AND ANSWERS WITH COMPLETE SOLUTIONS VERIFIED Terms in this set (99) Can a construction project finish successfully without being profitable? Yes, profitability is not a component of project success Contractor management personnel on a construction project: Always includes one Project Manager, two Superintendent, two area or trade superintendents, a field engineer, and an office engineer. Is the responsibility of the project financier/owner. Needs to be carefully formatted during the planning process to meet project cost and responsibilities. Always includes one Project Manager, one Superintendent, two area or trade superintendents, a field engineer, and two office engineers. Needs to be carefully formatted during the planning process to meet project cost and responsibilities. A component of cost control is accurately reporting actual costs and comparing them to the estimated costs. True Select the best answer in regard to construction project timelines vs. traditional/manufacturing project timelines: Construction project timelines conclude whenever all scopes are finished, while other industry projects are finite and end dates are usually chosen by the owner. Construction project timelines are finite and end dates are usually chosen by the owner, while other industry projects conclude whenever all scopes are finished. Both construction project timelines and other industry project timelines conclude whenever all scopes are finished. c. Both construction project timelines and other industry project timeline end dates are set by the project owner/investor. Construction project timelines are finite and end dates are usually chosen by the owner, while other industry projects conclude whenever all scopes are finished. Sticking to the original project schedule is crucial for completion of a successful project. A construction project schedule must not be modified during construction. False The estimator of a large project set the profit at $800,000 in the initial estimate. The project team completed the project on time and at the end of the job made $600,000 profit. When assessing the performance of this project, would this be considered a profitable project for the construction company? Yes/ no No

Meer zien Lees minder
Instelling
Vak

Voorbeeld van de inhoud

3/30/25, 9:37 CMGT 360 Exam |
AM
CMGT 360 EXAM QUESTIONS AND ANSWERS WITH COMPLETE
SOLUTIONS VERIFIED

Terms in this set (99)


Can a construction project finish Yes, profitability is not a component of project success
successfully without being profitable?

Contractor management personnel on a Needs to be carefully formatted during the planning process to meet project cost
construction project: and responsibilities.



Always includes one Project Manager,
two Superintendent, two area or trade
superintendents, a field engineer, and an
office engineer.


Is the responsibility of the project
financier/owner.


Needs to be carefully formatted during
the planning process to meet project cost
and responsibilities.


Always includes one Project Manager,
one Superintendent, two area or trade
superintendents, a field engineer, and
two office engineers.


A component of cost control is accurately True
reporting actual costs and comparing
them to the estimated costs.




1/24

,3/30/25, 9:37 CMGT 360 Exam |
AM
Select the best answer in regard to Construction project timelines are finite and end dates are usually chosen by the
construction project timelines vs. owner, while other industry projects conclude whenever all scopes are finished.
traditional/manufacturing project
timelines:


Construction project timelines conclude
whenever all scopes are finished,
while other industry projects are finite
and end dates are usually chosen by
the owner.



Construction project timelines are finite
and end dates are usually chosen by the
owner, while other industry projects
conclude whenever all scopes are
finished.


Both construction project timelines
and other industry project timelines
conclude whenever all scopes are
finished.
c. Both construction project timelines and
other industry project timeline end dates
are set by the project owner/investor.
Sticking to the original project schedule is False
crucial for completion of a successful
project. A construction project schedule
must not be modified during
construction.

The estimator of a large project set No
the profit at $800,000 in the initial
estimate. The project team completed
the project on time and at the end of
the job made
$600,000 profit. When assessing the
performance of this project, would this be
considered a profitable project for the
construction company?
Yes/ no
Which of the following are typical All the above are goals of a project
goals of a construction project?


The project is completed at or above the
specified level of quality



All the above are goals of a project



The project is completed safely



Project is finished under budget



Project is finished in accordance with the
project schedule




2/24

, 3/30/25, 9:37 CMGT 360 Exam |
AM
Why might construction projects be more Construction projects have unique attributes, such as locations vary, they are not
difficult to execute than manufacturing in controlled environments, and they are unique one-time endeavors
projects?


Construction projects are less difficult
than manufacturing projects



Manufacturing projects have unique
attributes, such as locations vary, they are
not in controlled environments, and they
are unique one-time endeavors



They are unsafe, overbudget,
endeavors which are out of control
and of low
quality


Construction projects have unique
attributes, such as locations vary, they are
not in controlled environments, and they
are unique one-time endeavors

According to FMI, a company's code of True
ethics must get buy-in from personnel in
order to be effective. true false

According to FMI, a company must have a True
system in place to report and act on
unethical employee behavior. True False

According to FMI, ethics and morals are False
attributes which people have and is not
something that can be taught or trained.
T/F

Owners may perceive contractors as True
unethical because the knowledge gap
that exists between the two parties. T/F

Which of the following is the best The moral principles which govern how members of a business conduct
definition of business ethics? themselves when making professional decisions



The moral principles which govern how
members of a business conduct
themselves when making
professional decisions


The application of individual moral values
in professional situations



The moral principles which govern how
an individual conducts them self



The application of individual moral
values (perception of right and wrong)
in day- to-day situations




3/24

Geschreven voor

Vak

Documentinformatie

Geüpload op
31 maart 2025
Aantal pagina's
24
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

€10,64
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF


Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
AcademicSuperScores Chamberlain College Of Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
299
Lid sinds
3 jaar
Aantal volgers
37
Documenten
7648
Laatst verkocht
2 weken geleden
AcademicSuperScores

NURSING, ECONOMICS, MATHEMATICS, BIOLOGY AND HISTORY MATERIALS. BEST TUTORING, HOMEWORK HELP, EXAMS, TESTS AND STUDY GUIDE MATERIALS WITH GUARANTEE OF A+ I am a dedicated medical practitioner with diverse knowledge in matters Nursing and Mathematics. I also have an additional knowledge in Mathematics based courses (finance and economics)

4,6

156 beoordelingen

5
125
4
9
3
11
2
5
1
6

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen