NCCER-OSHA SCAFFOLD SG
NEWEST EXAM WITH ACTUAL
QUESTIONS AND CORRECT
RATIONALES FOR GUARANTEED
PASS
Question-Erectors of a scaffold who exposed to potential falling object hazards shall be provided
with: - Answer-Over head protection
Question-The footing or anchorage for scaffolds must be capable of carrying the maximum
intended load without: - Answer-Tying or guying
Question-Osha requires a rest landing at intervals not exceed: - Answer-35 feet
Question-The top handrail of a scaffold must be able to withstand how many pounds of pressure?
- Answer-200
Question-When Building a scaffold inside a "goggle area" - Answer-Everyone inside the area
must wear goggles
Question-The ladder should be located on a mobile scaffold will not - Answer-tip over
Question-When should ties be installed? - Answer-During the erection process
, Question-What body produces the primary Code or regulations guiding the scaffolding industry?
- Answer-OSHA (Occupational Safety and Healthy Agency)
Question-What should be used to erect scaffolding on uneven ground? - Answer-Leveling Jacks
Question-OSAH specifically prohibits the use of? - Answer-Lean to scaffolds
Question-Boards or wooden pad placed on the soil to support scaffold legs are? - Answer-
Mudsills
Question-The tube of a tube and clamp scaffold is normally what size O.D.? - Answer-1.9 Inches
Question-Scaffold decks that overlap a minimum of how many inches, unless secured in some
other way? - Answer-12
Question-the bearer in a tube and clamp scaffold is always? - Answer-Placed above the adjacent
runner.
Question-What must a rolling scaffold have on each caster or roller? - Answer-Positive locking
device
Question-Who must inspect a scaffold each work shift and after any occurrence which could
effect a scaffold's structural integrity? - Answer-Competent person
NEWEST EXAM WITH ACTUAL
QUESTIONS AND CORRECT
RATIONALES FOR GUARANTEED
PASS
Question-Erectors of a scaffold who exposed to potential falling object hazards shall be provided
with: - Answer-Over head protection
Question-The footing or anchorage for scaffolds must be capable of carrying the maximum
intended load without: - Answer-Tying or guying
Question-Osha requires a rest landing at intervals not exceed: - Answer-35 feet
Question-The top handrail of a scaffold must be able to withstand how many pounds of pressure?
- Answer-200
Question-When Building a scaffold inside a "goggle area" - Answer-Everyone inside the area
must wear goggles
Question-The ladder should be located on a mobile scaffold will not - Answer-tip over
Question-When should ties be installed? - Answer-During the erection process
, Question-What body produces the primary Code or regulations guiding the scaffolding industry?
- Answer-OSHA (Occupational Safety and Healthy Agency)
Question-What should be used to erect scaffolding on uneven ground? - Answer-Leveling Jacks
Question-OSAH specifically prohibits the use of? - Answer-Lean to scaffolds
Question-Boards or wooden pad placed on the soil to support scaffold legs are? - Answer-
Mudsills
Question-The tube of a tube and clamp scaffold is normally what size O.D.? - Answer-1.9 Inches
Question-Scaffold decks that overlap a minimum of how many inches, unless secured in some
other way? - Answer-12
Question-the bearer in a tube and clamp scaffold is always? - Answer-Placed above the adjacent
runner.
Question-What must a rolling scaffold have on each caster or roller? - Answer-Positive locking
device
Question-Who must inspect a scaffold each work shift and after any occurrence which could
effect a scaffold's structural integrity? - Answer-Competent person