The BEST approach to network representation of a large and hugely
complex project is to ....... ANSWER .......Simplify network logic and
reduce it to the most meaningful relationships.
Use the Gantt chart and the activity list to determine when resource 5 is
free.
ActivityResourcesActivityResourcesA1F1B5G2C4H5D3J3E2K4 .......
ANSWER .......Between 45 and 60
The AOA network described by this table needs:
ActivityPredecessorA--B--CA, BDBEC, D ....... ANSWER .......One
dummy activity.
, Use the network diagram and activity lengths in the nodes to determine
the late finish time for activity C. ....... ANSWER .......14
Page | 2
The process of accelerating a project is referred to as: ....... ANSWER
.......Crashing
Activities C, D, and E in the project represented by the network are to be
hammocked. What are the early start and late finish times of the
hammock activity? ....... ANSWER .......6, 26
A project has the precedence requirements and activity durations shown
in the table. After he draws the network, the project manager decides that
activities H and I can be represented by a hammock activity. What are
the early start and late finish times associated with this hammock
activity?TimePredecessorA7
B8AC13BD8CE7AF6EG6AH11GI12HJ14D, F, I ....... ANSWER
.......13, 36
Use the network diagram and activity lengths in the nodes to determine
the early start time for activity D. ....... ANSWER .......14
In general, the better candidates for shortening are: ....... ANSWER
.......Early tasks opposed to later tasks.
Which of the activities in the diagram have slack? ....... ANSWER
.......B and D
, What information is NOT included in the nodes for an AOA network?
....... ANSWER .......Early Finish Time
Page | 3
What is the late start time for Activity E given the activity times and
precedence requirements shown in the table?
ActivityTimePredecessorA5--B7--C8AD7AE4BF8C, DG9E, FH7G
....... ANSWER .......17
It costs $75 per day for each day that a construction crew is on site. The
project manager determines that most activities can be crashed and has
listed the crashing costs next to the minimum time for each activity. Use
this information to determine the lowest cost for this project. All times
given are in days.ActivityNormal TimeMinimum TimeCrash Cost
($/day)PredecessorA106$70--B63$40--C22--
BD42$60CE64$80AF85$90D, E ....... ANSWER .......$1,780
Use the network diagram and activity lengths in the nodes to determine
the early finish time for activity G. ....... ANSWER .......26
Use the Gantt chart and activity list to determine when resource 3 is free.
ActivityResourcesActivityResourcesR3M1H1K5G4J3F2P1B2S2T4W3
....... ANSWER .......Between 10 and 20
Use the Gantt chart and activity list to determine which resource has the
greatest continual use.