One of the Scrum events is the Daily Scrum. What are two
outcomes of the Daily Scrum? Choose 2 answers - ANSWER--
An updated list of impediments for the Scrum Master to take
care of.
- A shared understanding of the most important work to be
undertaken next to achieve the best possible progress toward
the Sprint goal.
A Product Owner wants advice from the Scrum Master about
estimating work in
Scrum. Which of these is the guideline that a Scrum Master
should give? -
ANSWER-Product Backlog items must be estimated in
story points.
Who is responsible for clearly expressing Product Backlog
items? - ANSWER-
The Product
Owner
,A Development Team pulled a Product Backlog item into the
Sprint and worked on it. However, it does not meet their
definition of "Done" by the end of the Sprint. What three things
should happen with the incomplete Product Backlog item?
Choose 3 answers - ANSWER--Do not include the item in the
increment this Sprint.
-Do not show it in the Sprint Review.
-Re-estimate it and return it to the Product Backlog for the
Product Owner to decide what to do with it.
Which are NOT appropriate topics for discussion in a Sprint
Retrospective?
Choose 2 answers - ANSWER--Definition
of "Done".
-Sprint Backlog for the next
Sprint.
The Product Owner must release each increment to
production. - ANSWER-
When it makes
sense.
Who is responsible for forecasting the work estimates
during a Sprint? -
,ANSWER-The Development
Team.
What activities would a Product Owner typically undertake in
the phase between the end of the current Sprint and the start of
the next Sprint? - ANSWER-There are no such activities. The
next Sprint starts immediately after the current Sprint.
What are two good ways for the Development Team to make
non-functional requirements visible? Choose 2 answers -
ANSWER--Add them to the definition of "Done" so the work is
taken care of every Sprint.
-Add them to the Product Backlog and keep the Product Owner
posted on the expected effort.
You are the Scrum Master on a newly formed Scrum Team.
Which three of the following activities would probably help the
team in starting up? Choose 3 answers - ANSWER--Ensure the
team understands they need a definition of "Done".
-Have the Scrum Team members introduce themselves to each
other and give a brief background of their skills and work
history.
-Ask the Product Owner to discuss the product or project, its
history, goals, and context, as well as answer questions.
, What is it most appropriate for a Development Team to change
the definition of
"Done"? - ANSWER-During Sprint
Planning.
What are two responsibilities of testers in a Development
Team? Choose 2 answers - ANSWER-- Everyone in the
Development Team is responsible for quality.
- Scrum has no "tester" role.
What are the two primary ways a Scrum Master keeps a
Development Team
working at its highest level or productivity? - ANSWER-
- By removing
impediments that hinder the
Development Team.
- By facilitating Development Team
decisions.
For the purpose of transparency, when does Scrum say a
new increment of
working software must be available? - ANSWER-At the end
of every Sprint.