VERIFIED ANSWERS | GRADED A+ | GUARANTEED
PASS!!
___________ covers negligent actions by the contractor and the company's
employees, and includes bodily injury, property damage or loss, and other personal
injury such as slander or damage to reputation.
- answer-Commercial general liability
A building requires a 100-foot-long by 83-foot-wide by 5-inch-thick concrete slab.
Determine the number of 10-foot by 100-foot rolls of vapor barrier needed. The
vapor barrier needs to be lapped one foot. Hint: Subtract the lap from the width of
the roll
- answer-10 rolls
A building requires a 95-foot-long by 88-foot-wide by 6-inch-thick concrete slab.
Determine the cost to finish the slab using a productivity of 0.014 labor hours per
square foot and an average labor rate of $29.92 per labor hour.
- answer-$3502
A building requires a 95-foot-long by 88-foot-wide by 6-inch-thick concrete slab.
Using a waste factor of 10 percent, determine the number of cubic yards of
concrete needed to pour the slab.
- answer-171 CY
A commercial project requires the installation of 1,856 square feet of acoustical
ceiling. Using a productivity rate of 0.013 labor hours per square foot and a
productivity factor of 0.95, determine the number of adjusted labor hours required
,to install the ceiling.
- answer-23 lhr
An asphalt paving crew is used to pave a road 8,000 feet long. The road is 48 feet
wide and the paving machine can pave a 12-foot-wide strip of road during each
pass. The machine paves 13 lineal feet of 12-foot-wide road per minute. Two lifts
of asphalt are needed to pave the road. After completing a pass, it takes the crew
15 minutes to turn the paving machine around and get ready for the next pass. The
crew consists of a foreperson, seven operators, and a laborer. Using a system
efficiency of 45 minutes per hour, determine the number of labor hours required to
place 1 lineal foot of road 12 feet wide.
- answer-0.0157 Lahr/lft
During the construction of a recent office building, your company's framing crew
installed 515 lineal feet of 8-foot-high, metal-stud wall in two days. The crew
consisted of two carpenters and one helper and worked eight hours per day.
Determine productivity rate in labor hours per foot of wall for installing metal-stud
walls on this project.
- answer-.093 Lahr/lft
During the construction of a recent office building, your company's framing crew
installed 515 lineal feet of 8-foot-high, metal-stud wall in two days. The crew
consisted of two carpenters and one helper and worked eight hours per day.
Determine the number of labor hours to install 810 lineal feet of 8-foot-high,
metal-stud wall. If the crew consisted of a carpenter and laborer, how many days
would it take to frame the wall? They work eight hours per day.
- answer-4.7 days
Given the following information, determine the burdened hourly wage rate for a
carpenter. Assume the carpenters take full advantage of the retirement benefit.
Wage rate—$23.00 per hour
Hours worked—45 hours per week for 30 weeks, and 40 hours per week for 20
weeks
Vacation, holidays, and sick leave—Two weeks at 40 hours per week
Overtime—Time-and-a-half for any hours over 40 per week
Gas allowance—$150 per month
, Annual bonus—$300
Social Security—6.2 percent on the first $127,200 of wages
Medicare—1.45 percent of all wages
FUTA—0.6 percent on the first $7,000 of wages
SUTA—5.8 percent on the first $10,000 of wages
Worker's compensation insurance—$12.25 per $100.00 of wages
General liability insurance—0.55 percent of wages
Health insurance (company's portion)—$450 per month per employee
Retirement—$0.50 per $1.00 contributed by the employee on 6 percent of the
employee's wages
- answer-$34.45/hour
In __________ the contractor bases the bid on estimated quantities of work and on
completion of the work in accordance with the contract documents. Payments are
made based on the price that the contractor bids for each unit of work, and field
checks with measurements of work actually completed.
- answer-Unit-price agreement
Rebar is usually taken off in ______ of each size of bar and then converted into
__________.
- answer-Linear feet, weight
The ________ ensures that if a contractor is awarded the bid within the time
specified, the contractor will enter into the contract and provide all other specified
bonds
- answer-Bid bond
The ________ guarantees the owner that, within limits, the contractor will perform
all work in accordance with the contract documents, and that the owner will
receive the project built in substantial agreement with the documents.
- answer-Performance bond
The _________ comprises all of the work required for the completion of a project
and is the responsibility of a single prime contractor.