- A 'place concrete' activity requires the placement of 2080 cubic yards. If the individual production rate is 2 cubic yards per work hour per person, with a 10-person crew and 8 hour workday, how many days are needed to complete this activity? 
a.	13 
b.	26 
c.	104 
d.	130 - a. 13 
 
A topographical map is a drawing showing? 
a.	Subsurface soil conditions 
 b. A general profile view of the site 
c. Contour lines and elevations d. Cross sections along the length of the project - c. Contour l...
-